Mechanical Support Framing
DATA CENTER STUDY
![support-one Support](https://advanticllc.com/wp-content/uploads/2019/09/support-one-30x22.jpg)
PROJECT PROFILE
LOCATION
Dallas, TX
COMPLETED
2018
PROBLEM STATEMENT
Retrofit to support additional significant mechanical loads in an existing building corridor is expensive and time-consuming to design and install.
TIMELINE
![8-weeks](https://advanticllc.com/wp-content/uploads/2019/09/8-weeks-30x2.png)
ADVANTIC SCOPE
Advantic engineered the solution to meet project and code requirements, generated PE-stamped design documents and calculations, fabricated the structural system, and performed field installation support to a local trade already working at the job site.
![IMG_1066 - Copy Building](https://advanticllc.com/wp-content/uploads/2019/09/IMG_1066-Copy-23x30.jpg)
TECHNICAL APPROACH
Advantic Engineers utilized fiber-reinforced polymer structural profiles to meet Code-prescribed strength and serviceability criteria including seismic loads, and eliminated foundations by employing the existing slab. Project Managers facilitated BIM coordination with the mechanical trades and value-engineered connection details for the supported equipment.
![IMG_5513 Factory Floor](https://advanticllc.com/wp-content/uploads/2019/09/IMG_5513-30x22.jpg)
ECONOMICS
The fabricated cost was less than galvanized steel, and lead times were improved by 50-percent. Total installed cost was improved by more than 20-percent.